Suspension from Bidding against 株式会社井上組

株式会社井上組 (指名停止措置)
指名停止措置Shikoku Regional Development BureauJune 13, 2024

Action summary

Company
株式会社井上組Japanese only
Original: 株式会社井上組
Corporate Number: 6012801000155
Governing law
指名停止措置
指名停止措置
Action type
Suspension from Bidding
指名停止
Action date
June 13, 2024
Issuing authority
Shikoku Regional Development Bureau
四国地方整備局

Violation

Machine-translated summary — verify against original

In the construction of the P9 substructure of the Tsuda Elevated Bridge on the transverse road, contracted by the Tokushima River and National Highway Office of the Shikoku Regional Development Bureau, Inoue Corporation, a qualified contractor, used a pre-installed scaffolding for rebar assembly during the construction of the bridge pier. When the inclination of the rebar and scaffolding was confirmed and corrections were made, 142 vertical reinforcement bars (D51) had already been installed and collapsed, resulting in the death of one worker and injury to three others on the scaffolding. The accident occurred during the assembly of the reinforcement bars.

Show original Japanese text

上記有資格業者である(株)井上組は、四国地方整備局徳島河川国道事務所発注の「令和3年度横断道津田高架橋下部P9工事」において、橋脚躯体の施工にあたり、先行して設置した鉄筋組み立て用の架台を使用しての柱部鉄筋D51の組み立て(建込み)作業中、鉄筋及び架台の傾きが確認されたため、建てりを修正していたところ、既に建込んでいた142本の柱部鉄筋D51が倒壊して、架台上の足場に乗っていた一次下請の作業員1名が死亡し、3名が負傷する事故を発生させた。

Source

Original Shikoku Regional Development Bureau announcement (in Japanese)

The original Japanese disclosure is the authoritative record.

Watch this company

Get an email when 株式会社井上組 has new enforcement actions or registry changes (representative, address, business status). Sign-in is via a one-time email link — no password.

Company info

English name
株式会社井上組 Japanese only
Japanese name
株式会社井上組
Corporate Number
6012801000155
Registered address
東京都立川市砂川町八丁目17番地の2

About this recordAggregated and translated from public Japanese government disclosures. The English text is for reference only — authoritative content is the linked Japanese source.